Reorder Point Formula in Excel: When to Restock (with a Worked Example)

SubtbStudio · Updated 26 November 2026 · 3 min read

A reorder point is the stock level that should trigger a new order, early enough that the delivery arrives before you run out. You can set it by feel, but a short formula is more reliable, especially when sales change by season or suppliers are slow.

The formula

Reorder point = (Average daily sales × Lead time in days) + Safety stock
  • Average daily sales: units sold in a recent window (for example 30 days) divided by the number of days in that window. Use sales only, not damaged stock or samples, unless you also have to replace those.
  • Lead time: how many days pass between placing an order and putting the stock on the shelf. Use the supplier's typical time, not the best-case time.
  • Safety stock: a buffer for late deliveries or a sudden busy week. A simple start is one week of average sales. Increase it for unreliable suppliers or products you cannot afford to run out of.

A worked example

A 200g candle sold 42 units in the last 30 days. The supplier usually delivers in 7 days. You want about one week of safety stock.

InputValue
Units sold (30 days)42
Average daily sales42 ÷ 30 = 1.4
Lead time7 days
Demand during lead time1.4 × 7 = 9.8
Safety stock (7 days)1.4 × 7 = 9.8
Reorder point9.8 + 9.8 = 19.6, so 20 units

When on-hand stock falls to 20, you place an order. If sales stay at 1.4 a day and the delivery really takes 7 days, you will have about a week's stock left when the box arrives.

The same calculation in Excel or Google Sheets

Assume: units sold in the last 30 days in B2, the window length in C2 (30), lead time in days in D2, and safety-stock days in E2 (often the same as one week, or a bit more).

Daily sales:     =B2 / C2
Reorder point:   =ROUNDUP((B2/C2)*D2 + (B2/C2)*E2, 0)
Or shorter:      =ROUNDUP((B2/C2)*(D2+E2), 0)

ROUNDUP is safer than rounding down: a fraction of a unit still means you need one more on the shelf. If there were no sales in the window, B2 is 0 and the reorder point becomes 0, which is usually wrong for a product you still intend to stock; in that case set the point by hand or use a longer window.

Days of stock: a useful companion

Days of stock = On hand ÷ Average daily sales
             = F2 / (B2/C2)

Example: 28 units on hand and 1.4 sold per day is 20 days of stock. If lead time is 7 days, you still have time. If days of stock falls close to the lead time, you are already late to reorder.

Suggested order quantity

Once you are at or below the reorder point, a practical order size is the larger of your usual reorder quantity and the gap up to the reorder point:

=MAX(reorder_qty, reorder_point - on_hand)

Using a usual reorder quantity (for example a full carton, or enough for a month) avoids lots of tiny orders. Recalculate the reorder point after a busy season: Christmas sales should not set the point you use in February, unless you expect that demand to continue.

Formulas work in Excel 2016+, Microsoft 365, Google Sheets and LibreOffice. This is a planning method, not inventory-accounting advice.

This guide was drafted with AI assistance; the formulas and worked examples were checked in a spreadsheet before publishing.